July 19, 2022 update

Great progress continues on the new Folly Beach Fishing Pier as crews put the finishing touches on the diamond pierhead and gazebo while continuing to construct the substructure moving toward land. The gazebo roof is complete, fishing benches installed, and plumbing/electrical installation has begun on the diamond pierhead.

The first observation area is being framed as crews also work on installing the handrail and deck panels. Pile driving and precast setting continue toward land.

The substructure is approximately 70% complete with roughly 300′ worth of piles, caps, and beams remaining to be constructed. The new Folly Pier remains on schedule for completion in the Spring of 2023.

For more information on the Folly Pier project, and to watch a construction time-lapse, visit www.ccprc.com/PierProgress.